Article 1: workers participating in construction (including apprentices, interns, trainees and migrant workers) should be familiar with the safety technical operation procedures of their own type of work. 1n operation, they should stick to their posts and strictly prohibit drunk operation.

Article 2: electricians, welders, stokers, blasters, overweight drivers, pile drivers and various motor vehicle drivers must undergo special training, Article 3: the correct use of personal protective equipment and safety protection measures, enter the construction site, must wear a helmet, do not wear slippers or barefoot, in the absence of protective facilities under high altitude, cliff and steep slope construction, must wear safety belt, up and down cross operation, dangerous entrance and exit to have protective shed or other isolation facilities, Safety helmets, safety belts and safety nets shall be inspected regularly, and those that do not meet the requirements shall not be used.

Article 4: scaffolds, protective facilities, safety signs and warning boards on the construction site shall not be removed without authorization, and those that need to be removed shall be approved by the person in charge of the construction site.

Article 5: holes, pits, ditches and lifting openings on the construction site, There should be protective facilities or obvious signs at the funnel and other dangerous places.

Article 6: there should be traffic signs at the construction site. At the intersection with frequent traffic, there should be a command: on both sides of the railway crossing, there should be poles falling, in dangerous areas, there should be dangerous or no pass signs hanging, and red light warning should be set at night.

Article 7: the track gradient of small flat cars should not be greater than 3%, There should be a stop at the end of the rail, and the brake and hook of the vehicle should be in good condition and reliable.

Article 8: during the construction of the pit, the stability of the soil on the side wall should be checked frequently, and reinforcement measures should be taken at any time when cracks, looseness or support walking are found. According to the soil quality, ditch depth, water level, weight of mechanical equipment, the distance between the stacking materials and construction machinery and the pit side should be determined, and the materials should be transported to the pit, Signal communication should be applied.

Article 9: when preparing acid solution, acid should be slowly injected into water and stirred evenly. 1t is strictly forbidden to pour water into acid.

containers for storing acid should be covered and marked.

Article 10: do a good job in protecting female workers during menstruation, pregnancy, childbirth and lactation. When female workers are not competent for the original work during pregnancy, according to the doctor’s certificate, We solemnly declare that this article is a reprint of the network media, which only represents the author’s point of view and has nothing to do with this website. 1f the information column articles and comments violate your legal rights, please call to let us know and we will deal with them in time