the “three Simultaneities” system refers to that the occupational health and safety facilities of capital construction projects (Engineering), technical reconstruction projects (Engineering) and imported construction projects newly built, reconstructed and expanded in China must meet the national standards, and must be designed, constructed, put into production and use at the same time with the main project. 1n this regard, Article 53 of the labor law has made clear provisions

– safety technology facilities

– occupational health facilities

– auxiliary production facilities

the preliminary design of new construction, reconstruction and expansion projects can only be carried out after being examined and approved by the industry competent department, the administrative department of work safety, the health department and the trade union; After the completion of the project, it can be put into operation and use only after it has passed the completion acceptance of the competent department, the administrative department of work safety, the health department and the trade union

“three Simultaneities” system specifically includes the following contents:

– in the feasibility study of construction project, the demonstration of occupational health and safety must be carried out, and the preventive measures that may cause harm to employees must be clarified, and the demonstration results shall be loaded into the feasibility demonstration document

– when preparing the preliminary design documents of the construction project, the design unit shall prepare the special chapter on labor safety and health at the same time. The design of occupational health and safety facilities must comply with the national and industrial standards

– the construction unit must carry out the construction in accordance with the approved design documents, and shall not change the design of occupational health and safety facilities without authorization, and shall be responsible for the construction quality

– the completion acceptance of construction projects must be carried out in accordance with the relevant national regulations on occupational health and safety acceptance of construction projects. Those that do not meet the occupational health and safety standards shall not be accepted and put into operation

– after the construction project is accepted and officially put into operation, the occupational health and safety facilities shall not be left unused, and the production facilities and occupational health and safety facilities must be used at the same time